How to Build a Commissioning Workforce Plan

Commissioning teams are small compared with a peak construction workforce, but they are harder to staff. The people are specialists, they are needed for a defined window, and timing is unforgiving. Arrive too early and they sit idle while construction finishes. Arrive too late and completed systems wait for them. Building a commissioning workforce plan comes down to three things: defining the roles, sizing the team and timing mobilization against system turnover.

What is a commissioning workforce plan?

A commissioning workforce plan defines the roles, numbers, competencies and mobilization dates of the people needed to commission a facility, based on the systems to be commissioned and the order in which they will be turned over. It sits within overall workforce planning but follows its own logic.

Typical commissioning roles

RoleMain responsibility
Commissioning managerOverall commissioning plan and interfaces with construction and operations
System or area leadsDriving specific systems from turnover through commissioning
Discipline commissioning engineersMechanical, electrical, instrumentation and control, process
Commissioning techniciansTests, run-ins, loop checks and functional checks
Completions coordinatorTracking checks, punch items and system status in the database
Document controllerTest records and turnover packages
Vendor representativesPackage equipment checks and warranty requirements
Operations personnelRunning the plant during commissioning and startup

The wider set of project positions is covered in technical roles needed for oil and gas projects.

Step 1: Start from the system list

List every system and subsystem with its planned turnover date, complexity and discipline content. A utility air system and a compressor train do not need the same effort, and a headcount built without this list is a guess.

Step 2: Estimate effort per system

Count the work: loops, motors, valves, interlocks and procedures per system. Productivity data from earlier projects helps, adjusted for the client’s documentation and witnessing requirements, which can add a surprising amount of time.

Step 3: Build the histogram against turnover dates

Commissioning manpower should rise as systems are turned over, not before. The early team is small: the manager, system leads and completions staff building the database and procedures. Technicians build up as turnovers accelerate, and the peak usually comes with the main process systems and startup.

Step 4: Plan shift coverage for startup

Startup often runs around the clock. A plan that only covers day shift fails exactly when it matters most. Build night coverage and relief rotations into the plan from the start, especially for long startups.

Step 5: Manage the overlap with construction

Late in construction, both workforces are on site. Some construction personnel, particularly E&I technicians who installed the systems, can move into commissioning roles and bring useful system knowledge with them. Plan construction demobilization so that knowledge is not lost by accident.

Competency and selection

Commissioning roles need verified experience on similar systems. A CV that lists “commissioning” can mean anything from leading a startup to filling in test sheets. Structured technical interviews and reference checks are worth the time. Apex Core Engineering can assess candidates for commissioning roles through its manpower selection services, against the technical requirements of each position.

The team’s work begins at the gate described in the commissioning readiness checklist. For the overall scope, see industrial commissioning services.

Frequently asked questions

When should commissioning personnel be mobilized?

Leads and completions staff early in construction, technicians as system turnovers begin, with the peak around the main process systems and startup.

Can construction workers move into commissioning roles?

Some can, especially E&I technicians who installed the systems, provided they meet the competency requirements for the role.

How large should a commissioning team be?

It depends on the number and complexity of systems, the turnover schedule and the client’s documentation requirements, so it should be built up from the system list.