How to Select a Shutdown and Turnaround Support Partner

Choosing a turnaround partner is different from choosing a routine maintenance contractor. A maintenance contractor proves itself over months. A turnaround partner has to deliver hundreds of qualified people within days, perform safely and productively for a few intense weeks, and leave clean records behind. There is no time to recover from a poor choice once the plant is down. Here is how plant owners and maintenance managers can select a shutdown and turnaround support partner with confidence.

How is this different from selecting a maintenance partner?

Routine maintenance selection focuses on continuity, response times and long-term performance, as described in how to select an industrial maintenance partner. Turnaround selection focuses on surge capacity, planning maturity, supervision at scale and performance under time pressure.

What to evaluate

Relevant turnaround experience

Ask which turnarounds the partner has supported, on which unit types, with what peak workforce, and in what role. Experience in similar units, such as crude units, crackers or reformers, matters more than general shutdown experience. Ask for contacts at those plants and speak to them directly.

Planning capability

Can the partner contribute to scope development, work pack preparation and scheduling, or does it only supply labor? Early planning involvement usually pays back in execution.

Surge mobilization

How many qualified people can the partner mobilize, in which trades, and how quickly? Ask how it handles inductions, competency evidence and accommodation for large numbers. The steps involved are covered in turnaround workforce mobilization planning.

Supervision depth

Turnarounds need strong supervision on every shift, including nights. Ask for named superintendents and foremen, their turnaround history and the supervision ratios the partner plans to use.

Safety performance

Ask for safety statistics from previous turnarounds, how the partner manages high-risk work, and how it prepares a temporary workforce for a plant it does not know. The controls expected are described in turnaround safety management for high-risk work.

Quality and records

How will the partner ensure records are completed during the turnaround, not afterward? Ask to see sample work pack records from a previous job.

Comparison table

CriterionWhat to requestWarning sign
ExperienceReference turnarounds with unit types and peak numbersOnly general maintenance experience
PlanningSample work packs and schedules“We will follow your plan” with no planning capability
MobilizationTrade-by-trade availability and timelinesNumbers promised without names or sources
SupervisionNamed supervisors with turnaround historySupervisors to be recruited after award
SafetyTurnaround safety records and methodsNo turnaround-specific data
RecordsSample completed recordsRecords described as an end-of-job task

Check the partner’s bench

Turnaround partners draw on the same labor market as everyone else, and several plants in a region often schedule turnarounds in the same season. Ask what else the partner has committed to during your window, how many of the proposed people are its regular staff rather than new recruits, and what backup it has if another client’s turnaround overruns.

Commercial fit

Turnaround support is commonly contracted through unit rates, lump sums for defined packages, reimbursable arrangements for emergent work, or a mix. Whatever the model, agree upfront how discovery work is instructed and priced, and how disputes are handled without stopping work.

Involve the partner early

The best results come when the partner is selected early enough to take part in scope reviews, work pack preparation and readiness reviews. A partner that sees the work packs a week before shutdown is guessing at crew sizes and materials. The execution role a partner typically fills is described in plant turnaround execution support services.

Questions worth asking

  1. What went wrong on your last turnaround, and what did you change afterward?
  2. Who will lead our turnaround on your side, and what have they led before?
  3. How quickly can you replace a supervisor who is not performing?
  4. How do you keep productivity up on night shifts?

Apex Core Engineering supports shutdowns and turnarounds with planners, supervisors and multi-trade crews. Information on its work is available on its projects page.

Frequently asked questions

When should a turnaround support partner be selected?

Early enough to contribute to scope development and planning, often many months before the shutdown for major turnarounds.

Should a plant use one turnaround partner or several?

Many plants use a main partner for planning, supervision and core crews, with specialist contractors for specific activities.

What is the most important selection criterion?

Relevant turnaround experience combined with the ability to mobilize and supervise a large workforce safely at short notice.